The partnership draws on experience across contract mining, coal hauling, material handling, rehabilitation, processing and equipment support. This portfolio brings the partners' work into one place so that clients can explore the assignments most relevant to their requirements.

The portfolio combines projects undertaken by the individual partners, contributed leadership experience and equipment client relationships. Each entry identifies the nature of the experience and the partner bringing it to the collaboration.

Capability
TypePartner

Project experience

Project experience

MminaTlou Mine — iron-ore mining

TauSadi Mining and Engineering

Stated project capacity: 50,000 tonnes per month

TauSadi's current-project schedule records an iron-ore mining assignment for General Africa Mining at MminaTlou Mine, commencing on 15 May 2026. The schedule states a five-year duration and project capacity of 50,000 tonnes per month.

View experience
Project experience

Tlou Mining — materials handling

TauSadi Mining and Engineering

Stated project capacity: 140,000 tonnes per month

TauSadi's materials-handling assignment for Tlou Mining is recorded as commencing on 15 September 2026, with a stated three-year duration and project capacity of 140,000 tonnes per month.

View experience
Project experience

Wonderfontein Colliery — dump removal and rehabilitation support

TauSadi Mining and Engineering

Stated contract value: R29.7 million (VAT basis not supplied)

TauSadi was awarded a dump-removal contract at Wonderfontein Colliery in March 2023. The scope covered loading, hauling and placing topsoil, soft material and blasted hard material into voids or levelled areas in accordance with the mine's rehabilitation design and scheduling. The work also included maintenance of the haul roads used for the assignment. The client reference describes a truck-and-shovel fleet supported by dozers and auxiliary equipment, including water, grading and diesel-support equipment.

View experience
Project experience

Tweefontein — topsoil handling

TauSadi Mining and Engineering

TauSadi's reference information includes topsoil loading, hauling and placement at Tweefontein. The assignment contributes relevant experience in the controlled movement and placement of material within a mining environment.

View experience
Project experience

Glencore rehabilitation assignments — Zaaiwater, BMSE and Kliplaat

TauSadi Mining and Engineering

Average monthly work requirement: 150,000 cubic metres per month

TauSadi's rehabilitation experience includes dozing at Zaaiwater from November 2018 to November 2020. A subsequent Glencore reference also records work at Tweefontein Boschmans Southeast and Kliplaat in the two years preceding February 2024. The letter describes the use of D10 and D11 dozers and an average monthly dozing requirement of 150,000 cubic metres under the purchase order.

View experience
Project experience

Lurco — rail-loadout commissioning and coal loading

TauSadi Mining and Engineering

TauSadi provided operational services involving the commissioning of a rail-loadout facility and the subsequent loading of thermal-coal products onto trains for the export market.